Case Studies Archive | TDG Environmental
Home / Case Studies

SA 1800mm Patching Project

A regional road in South Australia required urgent structural repairs after a large sinkhole developed above three 1800mm culverts beneath the roadway, a key route for grain haulage.

Project Highlights

  • Large Diameter (DN1800) Patches: Nine 1800mm patches installed across three culverts, a major technical achievement.
  • Specialist Team Collaboration: South Australian operators worked closely with an experienced NSW specialist to ensure accuracy, safety, and quality.
  • Road Integrity Preserved: Repairs eliminated further sinkhole risk and avoided major road closures or full culvert replacement.

Stormwater Network Inspection and Condition Assessment

A regional council in northern New South Wales required a comprehensive inspection and condition assessment of its stormwater network to strengthen flood mitigation planning and inform future maintenance priorities.

Project Highlights

  • Extensive Network Coverage: End-to-end assessment of stormwater infrastructure with minimal community disruption.
  • Upgraded Data Storage: Councils data was uploaded to UtilityTrack for advanced insights to structural and serviceability grades
  • Hydrological Analysis: Coordination with engineering partners for a complete hydrological analysis of the network.
  • Efficient Project Execution: All works completed safely, on time, and within budget, in alignment with WSA standards

Duck Creek Contaminated Sediment Removal

A tidal channel in Sydney required the removal of asbestos-contaminated sediment to restore environmental safety and site integrity. The site presented complex conditions including limited access, tidal fluctuations, and a 1.4km haul route from the entry point. TDG Environmental was engaged by the client to deliver a compliant and efficient solution for safe waste removal, stockpile management, and site rehabilitation within a restricted tidal environment.

Project Highlights

  • Adaptive Equipment Strategy: Sourced and mobilised interstate Marooka Tracked Dumpers to improve mobility in deep tidal zones.
  • Safety and Compliance: Achieved full asbestos regulatory compliance with zero incidents.
  • Operational Efficiency: Completed sediment removal and site rehabilitation within the scheduled timeframe despite tidal and weather interruptions.
  • Environmental Stewardship: Maintained strict sediment controls and water management to prevent downstream contamination.

Vegetation Removal and Desilting works in Sydney

A canal in Sydney required vegetation removal and desilting works to restore proper water flow and reduce the risk of flooding during heavy rainfall. The site presented significant access challenges, including no ramp access and extremely tight working conditions. TDG Environmental was engaged to provide a solution that would overcome these limitations while ensuring safe and efficient removal of overgrowth and built-up sediment.

Project Highlights

  • Innovative Access Solution: Used the Grab Truck as a crane to overcome physical access barriers.
  • Efficient Vegetation Clearance: Green Climber slashed and collected dense overgrowth with precision.
  • Streamlined Debris Removal: Grab Truck enabled fast and efficient pickup of all consolidated material.

Canal Desilting and Vegetation Removal in Western Sydney

A heavily overgrown canal in Western Sydney required urgent desilting and vegetation removal to restore water flow and reduce the risk of flooding. Due to the steep embankments and absence of ramp access, traditional excavation methods posed significant safety risks. TDG Environmental was engaged to deliver a safe, efficient, and non-entry solution to clear the canal and prevent future blockages.

Project Highlights

  • Confined Space Risk Eliminated: All works completed using equipment, removing the need for personnel entry.

  • Flow Restored & Flooding Prevented: Full desilting and debris removal ensured unobstructed water movement.

  • Efficient, Non-Invasive Execution: Completed without ramping or major civil works, reducing time and risk on site.

Pipe Rehabilitation in Brisbane City

TDG Environmental successfully rehabilitated the sewer pipeline, achieving a fully sealed and structurally reinforced solution. The intervention prevented potential sinkholes, safeguarded the roadway, and ensured the long-term reliability of the asset.

Project Highlights

  • Enhanced Structural Durability: The CIPP patching method provided a 100-year design life, ensuring long-term pipeline integrity.

  • Prevention of Future Sinkholes: We eliminated any chance of a sinkhole forming, which could have compromised the road surface.

  • Client Satisfaction: The asset owner and client were very happy with the quality and efficiency of the work performed.

Power Pole Installation Impact on Local Infrastructure in NSW

A newly placed power pole was installed through an existing asset, causing a major obstruction and presenting a potential flood risk. The issue required a rapid and comprehensive intervention to prevent further damage and ensure the continued functionality of the affected infrastructure.

Project Highlights

  • Collaboration and Coordination: Close coordination between all involved teams was essential to manage the delicate excavation and repair process.
  • Innovative Techniques: The use of specialised equipment and innovative techniques demonstrated TDG’s commitment to providing high-quality, durable repairs.
  • Efficient Restoration: By utilising non-destructive digging, selective patching, and controlled concreting and backfilling, TDG ensured both the immediate and long-term success of the repair, reinforcing the asset without extensive replacement.

Sewer System Blockage Clearance in VIC

A severe sewer blockage obstructed 99% of a 1075mm diameter pipe located 30 metres underground, requiring urgent and complex intervention over a 2.5-week period.

Project Highlights

  • Collaboration and Coordination: Worked in partnership with the Utilities Client, Interflow contractors, and support teams from various locations to effectively manage the blockage.
  • Advanced Technology: Employed robotics from Queensland and specialised equipment from Truganina and Dandenong to enhance operational efficiency.
  • Team Effort: Acknowledged the dedication and hard work of the Geelong Depot team, Operations Scheduler, Ops Supervisor, Project Managers, and all operators involved.

Flood Recovery Works in QLD

Engaged to assist in flood recovery efforts for a regional council area, we set out to clean debris from 9 x 825mm pipes, including their inlets and outlets. Services provided: Kaiser Water Recycling Unit to allow for continuous cleaning operations, despite there being no onsite water An excavator and tipper to remove excess debris Traffic control measures to safely isolate the site from vehicle traffic A locator to identify underground assets, preventing any potential damage

Project Highlights

  • Collaboration: Efficient coordination of multiple work crews, including TDG operators and subcontractors, highlighted our commitment to health and safety and set a new standard for future projects.
  • Innovative Equipment: The use of the Kaiser Water Recycling Unit, along with an excavator and tipper, ensured continuous cleaning and safe debris removal, while traffic control and underground asset identification prevented potential site hazards.
  • Client Satisfaction: The successful completion of the flood recovery works not only met but exceeded our client’s expectations, laying a strong foundation for future collaborations and reinforcing our reputation for excellence.

TDG New Zealand Embarks on Lateral Lining Installations

The project’s main goal was to conduct lateral lining installations within wastewater connections, a task requiring a high degree of expertise and precision. Our team met this challenge with remarkable proficiency, delivering outstanding results that surpassed expectations.

Project Highlights

  • Site Engineering Excellence: Our skilled site engineer, meticulously coordinated the project, ensuring all prerequisites were in place. Her attention to detail and comprehensive approach were vital in laying the groundwork for the successful installation within Lower Hutt’s wastewater network. 
  • Team Dynamics and Collaboration: Our esteemed Reline group demonstrated exceptional synergy and efficient collaboration, setting a new standard for future projects. We prioritised health and safety procedures throughout, showcasing our unwavering commitment to our team and the community’s well-being. The group’s impressive cohesion and seamless teamwork were essential to the project’s success. 
  • Client Satisfaction: Our valued client, was thoroughly impressed with the culmination of our efforts in Lower Hutt. The successful completion of the liner installations not only met but exceeded their expectations, laying a solid foundation for future collaborations.